Cawsand Harbour

About This Project

Job:          Cawsand Harbour – Cornwall
Client:      CORMAC
Dates:      July 2016

iBEX carried out emergency de-scaling works together with an inspection of the cliff face below Garret Street in Cawsand following reports of loose material falling to beach level. The short notice emergency works project involved:

  • Closing the road above so ropes could be rigged from counterbalance weights behind parapet wall
  • Loose material was removed and dropped down to beach level
  • Site team had to work around the time in order to access all of the cliff
  • A survey of the cliff face was carried out detailing where material was removed from together with information on potential hazards